Arbor Day Celebrations Planned in Pittsfield

Print Story | Email Story
PITTSFIELD, Mass. — The Pittsfield Department of Community Development Parks and Recreation Program will be hosting two community Arbor Day events to celebrate the life and achievements of Robert L. Presutti.
 
Presutti is a longtime city resident who volunteered many hours with both the Parks Department and the Retired and Senior Volunteer Program (RSVP).
 
The first ceremony will take place on Friday, April 26 at 12 p.m. at the Berkshire Athenaeum, Bartlett Avenue side of the building. On Sunday, April 28 at 12 p.m., the city will host a Bob Presutti Tribute Day at Springside Park, located at 874 North Street. 
 
Both events will happen rain or shine and light refreshments will be provided.
 

Tags: arbor day,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Council OKs $3M Borrowing for Failing PHS Boilers

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The City Council has authorized the borrowing of $3 million for new boilers at Pittsfield High School — a project that was originally going to be funded by ARPA.

The nearly 100-year-old boilers are original to the building and have exceeded their useful life, officials say. They are converted locomotive engines that are extremely inefficient and expensive to maintain.

The replacement design was recently completed and a low bid was received. After looking at the numbers, it was clear that the allocated $1 million in American Rescue Plan Act funds would not be enough.

"$213,210 was spent on emergency repairs and the design work for the replacement project," Finance Director Matthew Kerwood confirmed in an email.
 
"The low and only bid for the replacement was $2,482,000, however given the complexity of this project I felt that a 20 percent contingency would be needed which gets to the $3,000,000 authorization. If the entire amount is not needed, the remaining unused balance will be rescinded at some point in the future."

The project is also time-sensitive, as one boiler is non-operational and another is severely compromised. If they fail during the heating season, the school will have to close.

"The contractor that was the low bid, in 30 days he can walk away from that bid if he wants to, and the other problem is I need to get this project underway to hopefully get them in and running by the time school reopens up for wintertime," Building Maintenance Director Brian Filiault explained.

"This is a major project, a major project. We're taking three locomotives out of that building and it's no easy thing. I mean, the building is built around it and we have a small portal that we actually will be able to get it out, we'll have to crane everything else. It's a very labor-intensive, very hard job, and I'm afraid of the timeframe because I can't run those boilers again. They've gone as far as they're going to go."