Grant Supports Berkshires Ecological Restoration, Climate Resilience

Staff Reports Print Story | Email Story
STOCKBRIDGE, Mass. — The Housatonic Valley Association (HVA) recently received a grant to support healthy aquatic systems and address climate change in the Berkshires.?
 
Funds were awarded by the Massachusetts Department of Fish and Game's Division of Ecological Restoration (DER) through its Regional Restoration Partnerships Program, which helps nonprofits and Regional Planning Agencies build capacity and advance ecological and aquatic restoration work.  
 
The nearly $200,000 grant will further support the Berkshire Clean, Cold, and Connected (BCCC) Restoration Partnership, a network of key stakeholders in Berkshire County working to keep the Hoosic, Housatonic, and Farmington River watersheds healthy. The BCCC Restoration Partnership is one of only three Partnership regions in the state to receive this funding.  
 
"Strong partnerships between the Commonwealth, regional organizations, municipalities, and non-profit organizations are critical for helping people and nature adapt to climate change. The Berkshire Clean, Cold, Connected Partnership catalyzes and supports river and wetland restoration projects throughout the region.?We are thrilled to support BCCC's work and can't wait to see what comes next," said DER Director Beth Lambert.?
 
Funding supports a full-time HVA Restoration Coordinator solely focused on facilitating collaboration between partners by helping them increase capacity to complete stream and wetland restoration work, which builds resilience for species and habitats as well as infrastructure and property threatened by climate change.  
 
BCCC core partners include the Berkshire Regional Planning Commission, the Berkshire Environmental Action Team, the Hoosic River Watershed Association, the Farmington River Watershed Association, and Trout Unlimited.   
 
Through these local and regional partnerships, HVA leads projects focused on habitat connectivity and green infrastructure by restoring degraded aquatic ecosystems that help reduce the adverse impacts of climate change. This includes dam removal, streamside buffer plantings, in-stream habitat enhancement, floodplain reconnection, polluted stormwater capture, and road-stream crossing replacements, or areas where a road crosses a stream. While bridges and culverts make it possible for people to get from one side of the stream to the other, some are outdated, restricting waterflow and threatening wildlife migration.?
 
"We are so grateful to DER for providing this transformational investment in the aquatic natural heritage of the Berkshires. The Restoration Partnerships Program is unique in recognizing what conservation practitioners like HVA and our BCCC partners need to make meaningful change on the ground. Our warming climate threatens both built and natural environments, and we've worked hard to find cost-effective projects that help ecosystems and communities adapt to this "new normal," which is impossible to ignore this year," said Mike Jastremski, HVA's Watershed Conservation Director. "DER Partnerships Program funding will help move those important projects forward, identify others for the future, and is the capacity-building glue needed to align the excellent work BCCC partners already do towards our shared vision of healthy streams and wetlands in Berkshire County."  
 
HVA also completed Road-Stream Crossing Management plans for the towns of Egremont, Richmond, and Great Barrington, and played a key role in helping all three receive DER Culvert Replacement Municipal Assistance (CRMA) Grant Program funds totaling nearly $160,000.?The CRMA program provides financial and technical assistance for municipalities to fix culverts that are flood risks and barriers to fish and wildlife movement. CMRA-funded projects were identified as high priorities in each community's Road-Stream Crossing Management Plan.
?
Overall, DER awarded $6.4 million in grants to help communities prepare for large storms, strengthen climate-ready infrastructure, restore flood storage capacities, and protect fisheries, wildlife, and river habitat.
 

Tags: grants,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

South County Road Maintenance

LEE, Mass. — The Massachusetts Department of Transportation (MassDOT) is announcing crews will be conducting daytime and overnight hour guardrail repair, drainage work, bridge repair, and tree trimming operations at various locations and times on I-90 eastbound and westbound during the week of Monday, May 20.

Lane closures will be in place during the construction operations and traffic will be able to travel through the work zones.  The schedule for the work and lane closures will be as follows: 

Otis/Blandford 

  • Guardrail and drainage work will be conducted on I-90 westbound between mile marker 22.0 to 26.6 from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Otis

  • Bridge repair operations will be conducted nightly on I-90 eastbound and westbound at mile marker 22.5, from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Blandford

  • Bridge repair operations will be conducted nightly on I-90 eastbound and westbound at mile marker 26.4 from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Russell

  • Tree trimming work will be conducted daily on I-90 westbound between mile marker 30.0 to mile marker 31.0, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day. 

Stockbridge/West Stockbridge

  • Guardrail and bridge repair work will be conducted nightly on I-90 eastbound and westbound from mile marker 3.0 to 6.0, from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Stockbridge

  • Bridge repair operations will be conducted daily on I-90 eastbound and westbound at mile marker 7.5, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day.

West Stockbridge

  • Bridge repair operations will be conducted daily on I-90 eastbound and westbound at mile marker 0.6, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day.

Lee

  • Drainage work will be conducted nightly on I-90 eastbound and westbound from mile marker 8.0 to 14.0, on Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Appropriate signage, law enforcement details, and messaging will be in place to guide drivers through the work area. 

Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.  

All scheduled work is weather dependent and subject to change without notice. 